| Notice Text: |
|
Bridgman Northbound Capacity Reduction (Posted 10/31/17) New: ANR will begin planned pipeline and compressor maintenance along its Michigan Leg North Segment located in the Northern Fuel Segment (Zone 7). This will reduce the total Bridgman Northbound (Loc ID #226632) capacity by the following: 360-MMcf/d (leaving 1,054-MMcf/d available) 11/1 - 11/14 Based on current nominations, it is anticipated that this posting may result in the capacity allocation reduction of IT and Firm Secondary volumes. This posting will be updated as more information becomes available.
For any questions regarding nominations or scheduling, please call the ANR Noms and Scheduling Hotline at: 1-800-827-5267 Please contact System Operations with any questions regarding operations or facilities. Monica Edwards 832-320-5822 Operations Control Howard Earl 832-320-5855 Gas Control |
|