Willow Run Capacity Reduction (Posted 8/8/17)
New: ANR will begin planned pipeline maintenance between its Defiance Compressor Station and Willow Run Meter Station located in the Northern Area (Zone 7), which will result in the following capacity reduction:
Willow Run Delivery (DRN #42078)
148-MMcf/d (leaving 609-MMcf/d available) 9/14 - 9/21
Based on current nominations, it is anticipated that the above reductions will have no impact to services. This posting will be updated as more information is available.
For any questions regarding nominations or scheduling, please call the ANR Noms and Scheduling Hotline at:
1-800-827-5267
Please contact System Operations with any questions regarding operations or facilities. Monica Edwards 832-320-5822 Operations Control Howard Earl 832-320-5855 Gas Control |
|