Critical Notice

TSP:006958581
TSP Name:ANR Pipeline Company

Notice Type Desc: Other
Posting Date/Time: 08/01/2017 13:30
Notice Effective Date/Time: 08/01/2017 13:30
Notice End Date/Time: 08/02/2018 08:59
Notice ID: 8245
Notice Status Desc: Initiate
Prior Notice:  
Reqrd Rsp: 5
Rsp Date/Time:  
Subject: Niles Power Plant Meter Station Project Capacity Reservation Posting
Notice Text:
Reservation of Capacity Posting

Pursuant to Section 6.3.3 of the General Terms and Conditions of its FERC Gas Tariff, ANR Pipeline
Company (ANR) gives notice that Unsubscribed Capacity, as more fully described below, will be reserved
for use in a future expansion of ANR's system. The Niles Power Plant Meter Station Project (the "Project") is being
proposed to construct and modify certain metering equipment and other ancillary facilities to provide firm
transportation service that is currently anticipated to be used by shipper(s) in association with the proposed Indeck
Niles Power Plant in Cass County, Michigan. The estimated Project in-service date is August 1, 2020. The
expansion open season for the Project was conducted from June 29, 2017 to July 10, 2017.

ANR is reserving annual transportation capacity as more fully described below for the following segment:

St. John Eastbound (Loc ID 226633): 111,951 Dth/day Annual starting August 1, 2020

Prior to this notice, the subject capacity was posted as generally available capacity along the applicable ANR capacity segment. ANR will make this capacity available for sale on a limited term basis starting from the date of this posting until the projected in-service date of the Project as described above. If any of this reserved capacity is sold on a limited-term basis that would otherwise be eligible for a right of first refusal or if there are any material changes in the scope of the expansion project, ANR will update this posting accordingly.