Critical Notice

TSP:006958581
TSP Name:ANR Pipeline Company

Notice Type Desc: Maint
Posting Date/Time: 10/05/2016 09:50
Notice Effective Date/Time: 10/05/2016 09:50
Notice End Date/Time: 10/28/2016 08:59
Notice ID: 7876
Notice Status Desc: Supersede
Prior Notice: 7864
Reqrd Rsp: 5
Rsp Date/Time:  
Subject: Southeast Area Capacity Reduction (Updated 10/5/16) Update: ANR has extended the capacity restriction for the SE 2A (Eunice-E)-CFTP (DRN #226641) (See PSO ID #7876)
Notice Text:
Southeast Area Capacity Reduction (Updated 10/5/16)
This posting supersedes PSO ID#7864

Due to current pipeline conditions and planned pipeline and compressor maintenance, ANR is limiting eastbound nominations pathed through the SE 2A (Eunice-E)-CFTP (DRN #226641) to the following:

380-MMcf/d - 10/5 - 10/11
200-MMcf/d - 10/12 - 10/27

Based on current eastbound nominations through the Eunice Compressor Station, it is anticipated that the above reductions will result in the curtailment of IT and Firm Secondary nominations. This posting will be updated as more information becomes available.

For any questions regarding nominations or scheduling, please call the ANR Noms and Scheduling Hotline at:

1-800-827-5267

Please contact System Operations with any questions regarding operations or facilities.
Monica Edwards 832-320-5822 Operations Control
Howard Earl 832-320-5855 Gas Control