Notice Text: |
|
Southwest Mainline Capacity Reduction (Updated 12/14/15)
ANR continues the planned pipeline maintenance on its SWML Southwest Central Fuel Segment (ML - 6). Additionally, ANR will begin compressor maintenance at its New Windsor Compressor Station located in Henry County, Illinois, which will reduce the total SWML - CFTP (DRN#226630) capacity by the following:
86-MMcf/d (leaving 633-MMcf/d available) 12/14 - 3/31/16
Based on current nominations through the SWML, it is anticipated that the above reductions may result in the curtailment of IT and Firm Secondary nominations. This posting will be updated as more information becomes available.