Notice Text: |
|
SW Area Capacity Restriction (Posted 12/2/15)
ANR will begin planned pipeline maintenance west of the Custer Compressor Station located in Custer County, Oklahoma, in the Southwest Area. During the period of December 15th through December 19th, the total receipt capacity between the E.G. Hill and Custer Compressor Stations (Gageby SW1- DRN #233839) will be limited to 200-MMcf/d.
Based on current nominations, it is anticipated the above reductions will result in the curtailment of nominations associated with IT and Firm Catalog Receipt points in the affected area. Also, interconnects along this segment may experience higher line pressures. This posting will be updated as more information becomes available.
For any questions regarding nominations or scheduling, please call the ANR Noms and Scheduling Hotline at:
1-800-827-5267
Please contact System Operations with any questions regarding operations or facilities. Paul Oliver 832-320-5885 Howard Earl 832-320-5855 |
|