Notice Text: |
|
Southwest Mainline Capacity Reduction (Posted 11/23/15)
ANR will begin planned pipeline maintenance on its SWML Southwest Central Fuel Segment (ML - 6), which will reduce the total SWML - CFTP (DRN#226630) capacity by the following:
45-MMcf/d (leaving 674-MMcf/d availble) 12/1 - 3/31/16
Based on current nominations through the SWML, it is anticipated that the above reductions may result in the curtailment of IT and Firm Secondary nominations. This posting will be updated as more information becomes available.
For any questions regarding nominations or scheduling, please call the ANR Noms and Scheduling Hotline at:
1-800-827-5267
Please contact System Operations with any questions regarding operations or facilities. Paul Oliver 832-320-5885 Howard Earl 832-320-5855 |
|