Critical Notice

TSP:006958581
TSP Name:ANR Pipeline Company

Notice Type Desc: Maint
Posting Date/Time: 10/21/2015 10:55
Notice Effective Date/Time: 10/21/2015 10:55
Notice End Date/Time: 04/01/2016 08:59
Notice ID: 7581
Notice Status Desc: Supersede
Prior Notice: 7344
Reqrd Rsp: 5
Rsp Date/Time:  
Subject: Tie Line Capacity Reduction (Updated 10/21/15) Updated: ANR continues planned and unplanned engine maintenance on its Tie Line. (See CN ID #7581)
Notice Text:
Tie Line Capacity Reduction (Updated 10/21/15)
(This posting Supersedes CN ID #7344)

ANR continues planned and unplanned engine maintenance at the LaGrange Compressor Station located in Indiana in the Northern Fuel Segment (ML-7). ANR will reduce the total LaGrange E-W CFTP (DRN #314515) capacity by the following:

130-MMcf/d (leaving 497-MMcf/d available) 10/21 - 10/31
155-MMcf/d (leaving 527-MMcf/d available) 11/1 - 3/31/2016

Based on current nominations, it is anticipated that the above reduction may impact IT or Firm Secondary nominations.

This posting will be updated as more information becomes available.

For any questions regarding nominations or scheduling, please call the ANR Noms and Scheduling Hotline at:

1-800-827-5267

Please contact System Operations with any questions regarding operations or facilities.
Paul Oliver 832-320-5885
Howard Earl 832-320-5855