Critical Notice

TSP:006958581
TSP Name:ANR Pipeline Company

Notice Type Desc: Force Maj
Posting Date/Time: 09/01/2025 09:10
Notice Effective Date/Time: 09/01/2025 09:10
Notice End Date/Time: 09/03/2025 08:59
Notice ID: 12549
Notice Status Desc: Supersede
Prior Notice: 12548
Reqrd Rsp: 5
Rsp Date/Time:  
Subject: LIFTED: NOTICE OF FORCE MAJEURE ANR Pipeline Company - Southeast Mainline - Cottage Grove Southbound (Lifted: 9/1/25)
Notice Text:
LIFTED: NOTICE OF FORCE MAJEURE ANR Pipeline Company - Southeast Mainline - Cottage Grove Southbound (Lifted: 9/1/25)

Effective Tuesday, September 2, 2025, Timely Cycle, ANR is lifting the Force Majeure capacity restrictions at Cottage Grove Southbound (LOC #505614) and reinstating to 936 MMcf/d.

Please refer to Notice #12536 for additional capacity impacts.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267