Notice Text: |
|
UPDATED: CAPACITY REDUCTION Southwest Mainline Northbound (Updated: 7/8/25)
Since the last posting, ANR has revised the capacity impact from the maintenance on the Southwest Mainline at the Havensville compressor station. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Capacity will be reduced as follows:
Effective 7/9 - 7/20 Southwest Mainline Northbound (LOC #226630): 206 MMcf/d (leaving 500 MMcf/d)
Estimated impact to Firm Primary as follows: 0% - Based on the Current Net Shipper Nominations 24% - Based on the Current Contracted MDQ 7/21 - 7/25 Southwest Mainline Northbound (LOC #226630): 196 MMcf/d (leaving 510 MMcf/d)
Estimated impact to Firm Primary as follows: 0% - Based on the Current Net Shipper Nominations 23% - Based on the Current Contracted MDQ
7/26 - 8/3 Southwest Mainline Northbound (LOC #226630): 156 MMcf/d (leaving 550 MMcf/d) Estimated impact to Firm Primary as follows: 0% - Based on the Current Net Shipper Nominations 17% - Based on the Current Contracted MDQ
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract. Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
|
|