Critical Notice

TSP:006958581
TSP Name:ANR Pipeline Company

Notice Type Desc: Plnd Outage
Posting Date/Time: 06/25/2025 10:16
Notice Effective Date/Time: 07/04/2025 09:00
Notice End Date/Time: 08/12/2025 08:59
Notice ID: 12427
Notice Status Desc: Initiate
Prior Notice:  
Reqrd Rsp: 5
Rsp Date/Time:  
Subject: CAPACITY REDUCTION Southwest Mainline Northbound (Posted: 6/25/25)
Notice Text:
ANR has planned maintenance on the Southwest Mainline. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Capacity will be reduced as follows:

7/4 - 7/10 Southwest Mainline Northbound (LOC #226630): 116 MMcf/d (leaving 590 MMcf/d)

Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
11% - Based on the Current Contracted MDQ

7/11 - 7/25 Southwest Mainline Northbound (LOC #226630): 176 MMcf/d (leaving 530 MMcf/d)

Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
20% - Based on the Current Contracted MDQ

7/26 - 8/11 Southwest Mainline Northbound (LOC #226630): 116 MMcf/d (leaving 590 MMcf/d)

Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
11% - Based on the Current Contracted MDQ

Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267