UPDATED: CAPACITY REDUCTION Michigan Leg South - St. John Eastbound (Updated: 4/22/25)
Since the last posting, ANR has included the estimated Firm Primary % impact of the maintenance on Michigan Leg South. All other aspects of the posting remain unchanged. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:
4/21 - 4/22 St. John Eastbound (LOC #226633): 287 MMcf/d (leaving 1038 MMcf/d)
Estimated impact to Firm Primary as follows: 0% - Based on the Current Net Shipper Nominations 0% - Based on the Current Contracted MDQ
4/23 - 4/27 St. John Eastbound (LOC #226633): 575 MMcf/d (leaving 750 MMcf/d)
Estimated impact to Firm Primary as follows: 0% - Based on the Current Net Shipper Nominations 19% - Based on the Current Contracted MDQ
4/28 - 4/29 St. John Eastbound (LOC #226633): 454 MMcf/d (leaving 871 MMcf/d)
Estimated impact to Firm Primary as follows: 0% - Based on the Current Net Shipper Nominations 5% - Based on the Current Contracted MDQ
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract. By means of this notice, ANR is establishing which specific Gas Days will be included when determining a shipper's 7-day Non-Force Majeure Average Usage Quantity pursuant to Section 6.36.2(b) of the Tariff.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
|
|