Critical Notice

TSP:006958581
TSP Name:ANR Pipeline Company

Notice Type Desc: Force Maj
Posting Date/Time: 03/23/2025 12:10
Notice Effective Date/Time: 03/23/2025 12:10
Notice End Date/Time: 04/04/2025 08:59
Notice ID: 12272
Notice Status Desc: Initiate
Prior Notice:  
Reqrd Rsp: 5
Rsp Date/Time:  
Subject: NOTICE OF FORCE MAJEURE ANR Pipeline Company - Southeast Mainline - Cottage Grove Southbound (Posted: 3/23/25)
Notice Text:
NOTICE OF FORCE MAJEURE ANR Pipeline Company - Southeast Mainline - Cottage Grove Southbound (Posted: 3/23/25)

This is to notify all contracted parties of ANR Pipeline Company ("ANR") that pursuant to Section 6.7 of ANR's FERC Gas Tariff, ANR has declared a Force Majeure event in effect for natural gas transactions on the Southeast Mainline due to an uncontrollable and unexpected equipment failure at the Cottage Grove compressor station, Unit 607. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:

3/23 (Intraday) Cottage Grove Southbound (LOC #505614): No incremental volumes will be scheduled.
3/24 - 3/31 Cottage Grove Southbound (LOC #505614): 315 MMcf/d (leaving 968 MMcf/d)

Estimated impact to Firm Primary as follows:
12% - Based on the Current Net Shipper Nominations
18% - Based on the Current Contracted MDQ

4/1 - 4/3 Cottage Grove Southbound (LOC #505614): 296 MMcf/d (leaving 936 MMcf/d)

Estimated impact to Firm Primary as follows:
15% - Based on the Current Net Shipper Nominations
21% - Based on the Current Contracted MDQ

Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Force Majeure Average Usage Quantity, as defined in Section 6.36.2(a) of ANR's Tariff, less any scheduled quantities on the contract. By means of this notice, ANR is establishing which specific Gas Days will be included when determining a shipper's 7-day Force Majeure Average Usage Quantity pursuant to Section 6.36.2(a) of the Tariff.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267