Critical Notice

TSP:006958581
TSP Name:ANR Pipeline Company

Notice Type Desc: Plnd Outage
Posting Date/Time: 12/11/2024 14:15
Notice Effective Date/Time: 12/11/2024 14:15
Notice End Date/Time: 01/17/2025 08:59
Notice ID: 12112
Notice Status Desc: Supersede
Prior Notice: 12086
Reqrd Rsp: 5
Rsp Date/Time:  
Subject: UPDATED CAPACITY REDUCTION Southwest Mainline Northbound (Updated: 12/11/24)
Notice Text:
UPDATED CAPACITY REDUCTION Southwest Mainline Northbound (Updated: 12/11/24)

Since the last posting, ANR has extended the pipeline maintenance on the Southwest Mainline. As a result, capacity will be reduced as follows:

11/22 - 1/17 (previously 12/17) Southwest Mainline Northbound (LOC #226630): 46 MMcf/d (leaving 685 MMcf/d)

ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
4% - Based on the Current Contracted MDQ

Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.