Critical Notice

TSP:006958581
TSP Name:ANR Pipeline Company

Notice Type Desc: Plnd Outage
Posting Date/Time: 09/20/2024 17:35
Notice Effective Date/Time: 09/30/2024 09:00
Notice End Date/Time: 10/08/2024 08:59
Notice ID: 12013
Notice Status Desc: Supersede
Prior Notice: 11995
Reqrd Rsp: 5
Rsp Date/Time:  
Subject: UPDATED: CAPACITY REDUCTION Southwest Mainline Northbound (Updated: 9/20/24)
Notice Text:
UPDATED: CAPACITY REDUCTION Southwest Mainline Northbound (Updated: 9/20/24)

Since the last posting, ANR has adjusted the capacity impact for the pipeline maintenance on the Southwest Mainline. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:

9/30 - 10/1 Southwest Mainline Northbound (LOC #226630): 181 MMcf/d (leaving 525 MMcf/d)

Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
21% - Based on the Current Contracted MDQ

10/2 - 10/7 Southwest Mainline Northbound (LOC #226630): 146 MMcf/d (leaving 560 MMcf/d)

Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
16% - Based on the Current Contracted MDQ

Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule and deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267