Notice Text: |
|
UPDATED: CAPACITY REDUCTION Southwest Mainline Northbound (Updated: 9/20/24) Since the last posting, ANR has adjusted the capacity impact for the pipeline maintenance on the Southwest Mainline. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:
9/30 - 10/1 Southwest Mainline Northbound (LOC #226630): 181 MMcf/d (leaving 525 MMcf/d)
Estimated impact to Firm Primary as follows: 0% - Based on the Current Net Shipper Nominations 21% - Based on the Current Contracted MDQ
10/2 - 10/7 Southwest Mainline Northbound (LOC #226630): 146 MMcf/d (leaving 560 MMcf/d)
Estimated impact to Firm Primary as follows: 0% - Based on the Current Net Shipper Nominations 16% - Based on the Current Contracted MDQ
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule and deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.